Performance Tests Overview

The performance verification tests are designed to provide the highest level of confidence that the instrument being tested conforms to the published, factory-set specifications. The tests are designed to test an instrument operating within the temperature range defined by the instrument specifications.

The calibration procedure for the M9485A VNA is unique among other TME applications. Refer to the Detailed Calibration Procedure for complete instructions.

In all test equipment configurations, cables and adapters must be properly torqued. Exceeding recommended torque values can cause damage to a cable or adapter, and can cause inaccurate test results.

The recommended calibration cycle is every 12 months. Performance tests are listed in the order that they should be performed. Click on the links below to go to the test topic page.

To successfully complete the module calibration, all performance tests must be run and passed within 14 days to run the Store Cal Info to Module test. (Does not apply to the M9378A/B directional coupler modules.)

Performance tests for the M9376A receiver module:

  1. Power Correction Calibration

  2. Receiver Compression

  3. Dynamic Accuracy — 1 MHz

  4. Noise Floor

  5. Dynamic Accuracy — 1.195 GHz

  6. Trace Noise

  7. Uncorrected System Performance

  8. Maximum Leveled Power

  9. Store Cal Info to Module

Performance tests for the M9377A direct access receiver module:

  1. Power Correction Calibration

  2. Receiver Compression

  3. Dynamic Accuracy — 50 MHz

  4. Dynamic Accuracy — 1.195 GHz

  5. Return Loss

  6. Noise Floor

  7. Maximum Leveled Power

  8. Store Cal Info to Module

Performance tests for the M9378A/B directional coupler module:

  1. Test Coupler

  2. Reference Coupler

  3. Attenuator

  4. Bias Tee (M9378B only)

Performance test for the M9340A distributor module:

  1. Frequency Response Gain and Output Power

  2. Store Cal Info to Module